Torrens Project

The Torrens Project (EL5614) is a joint venture between Aeris Resources (70% interest) and Kelaray Pty Ltd (a wholly owned subsidiary of Argonaut Resources NL) and is exploring for iron-oxide copper-gold (IOCG) systems.

EL5614 is located within the highly prospective Stuart Shelf Region of South Australia and lies within 50 kilometres of Oz Minerals’ Carrapateena deposit and 75 kilometres from BHP’s Olympic Dam mine. The Torrens Anomaly, a large regionally significant coincident magnetic and gravity anomaly with a footprint in excess 160km2 (larger footprint than Olympic Dam) is located within EL5614.

Within the Torrens Project area, geophysical modelling/interpretation has identified 28 geophysical anomalies based on gravity and magnetic geophysical datasets.  Of the 28 anomalies identified, 12 are based on gravity only anomalies[1].

 

[1] A gravity only anomaly in the Eastern Gawler Craton can be associated with a range of different geological rock/alteration features including but not limited to an IOCG system.

 

 

 

Limited drilling, totalling six drill holes between 1977 and 2008 defined a large magnetite dominant with lesser hematite alteration system interpreted to form the distal component of a large IOCG system.  Zones of anomalous copper mineralisation (≥0.1% Cu) were intersected from several drill holes with the most significant mineralised zone associated with TD2 (246m @ 0.1% Cu).

Exploration activity on the project had been suspended since 2008 due to uncertainty regards the Native Title status of the project area, and Aboriginal Heritage restrictions.

On 9th August 2016, Justice Mansfield of the Federal Court handed down his decision on the Lake Torrens Overlap Proceedings (No3). These proceedings were in respect of overlapping applications for a determination of native title rights over the lands and water of Lake Torrens, claimed by three separate native title claimant groups.  The Torrens Project EL5614 is located within the disputed claim area.  Justice Mansfield ruled that none of the overlapping claims had been proved.  All claimants have made appeals to the full court.  The court has not yet made a decision on the appeals and it may dismiss all the appeals.  In the interim, the effect of the Mansfield decision is that the area of the project has no Native Title granted, nor any recognised Native Title claimants.

On 31 March 2017 the joint venture partners were granted a summary determination by the South Australia Environmental Resources and Development Court, in the absence of any Native Title claimants, of the Native Title authority for the conduct of exploration activities on EL5614  This allows the joint venture to submit the plan of activity with supporting environmental impact assessments. The State regulators will review and can approve the exploration activities.

On the 15 February 2018, the South Australian Minister for Aboriginal Affairs and Reconciliation approved an application by the Torrens Joint Venture under Section 23 of Aboriginal Heritage Act 1988. The authorisation allows for up to 70 deep diamond drill holes over an area of 120km² over the Torrens geophysical anomalies. This was the final approval required to enable the Torrens Joint Venture to proceed with on-ground exploration activities, including a major drill program.

An airborne gravity survey was flown over the entire exploration tenement (EL5614) during the March 2018 quarter. The high resolution gravity survey supersedes previous gravity data compilations dating back to the 1970s. The increased accuracy from the new gravity survey will better define rock density contrasts which will be used to more accurately define prospective targets for drilling.

 

 

2018 residual gravity image over the Torrens Project area and 2006 residual gravity image over the Olympic Dam deposit

 

On 5 December 2018, Aeris announced that the drilling and helicopter support contracts had been awarded in preparation for the upcoming drill program at Torrens.  Mobilisation of equipment is to commence mid December with drilling to targeted to commence in mid January 2019.

The drilling program will be heli-supported utilising a specialised heli-portable drill rig.  Ten 6m x 2.8m raised work platforms will be transported by helicopter onto the lake and bolted together to act as a stable platform on the lake surface.  The drill rig will be flown onto the platform in 16 sections and then re-assembled on the platform.  Personnel, equipment, drill consumables and other materials will be transported via helicopter from the exploration camp to the work platform on the lake surface.

The Stage 1 drilling campaign will consist of 8-10 drill holes focusing on the highest priority targets.  The Torrens anomaly sits under approximately 400m of cover and drill holes are expected to be between 700m and 1,500m depth.

Torrens Gravity Anomalies