Overview 

There are four additional mine projects scheduled for future production, which together with Tritton and Murrawombie form the current Life of Mine plan (LOM). These projects will supplement and then replace production from Tritton and Murrawombie as the latter are exhausted.

Brownfields exploration at the Tritton deposit has identified a number of opportunities to extend the life of the operation, including extensions to the current Mineral Resource.  Importantly, both the Tritton and Murrawombie deposits remain open at depth.  

Aeris is confident that drilling will grow these known deposits and that mine life will progressively extend. Exploration success in finding new deposits in this highly prospective region could increase production rates and/or increase the life of the operation. 

Tritton Underground Mine

The Tritton deposit is a large, (over 20 million tonne), copper dominant sulphide system, discovered in the mid 1990s via geophysical methods.

Mining of the Tritton orebody commenced in 2004 with the development of an access decline and construction of a sulphide ore processing plant. Copper is extracted via conventional crushing and flotation circuits producing a copper concentrate. Stope production commenced in March 2005. In its first year of production, Tritton produced 23,088 tonnes of copper in concentrate.

Tritton reached 10 years of production in 2015 with significant Mineral Resource remaining. As at 30 June 2019, the combined Measured, Indicated and Inferred Tritton Mineral Resource Estimate is 9 million tonne at 1.3% Cu for 120 thousand tonne of copper metal.  Find out more

The Tritton Underground Mine successfully transitioned to a new mine design in response to a change in orebody geometry, with changes to stope extraction sequence on the lower levels to eliminate pillar stopes. 

Additional upgrades to the ventilation circuit  were completed in 2017 to sustain ore production at more than a million tonnes per annum.  This investment, together with  changes to the mining sequence have set Tritton up for stable stope production in coming years as mining extends at depth.

Aeris is committed to continued investigation and investment into mining equipment and technology.  Some recent examples have included a significant upgrade of the tele-remote loader operation system allowing loading operations to be conducted from the surface control room, and bogging ore from the stopes to be continued during blast clearance and shift changes.

Tritton Underground Mine Section View 

Tritton Mine Extensions

Opportunities exist to extend mining operations at Tritton from a number of sources:
• Tritton main deposit extensions at depth;
North wing; and
Budgerygar deposit access through Tritton.   
 
Resource drilling of depth extensions to Tritton is planned in FY2020, to be followed by mine design and economic analysis of how to mine the deposit at a depth of up to 1,500 metres below the surface. The mineralisation is known to extend to this depth; however a lack of drilling prevents the design of mine extension. Finding sufficient Mineral Resources at an economic copper grade is necessary before design of the access decline and other infrastructure can proceed. 
 

Murrawombie Underground Mine

The Murrawombie deposit is located in the southern area of the Girilambone Complex.

The development of Murrawombie commenced in 2016 and the mine reached full production rates during 2018.  Strategically, Murrawombie was developed to replace the now exhausted North East and Larsen underground mines.The development of Murrawombie commenced in 2016 and the mine reached full production rates during 2018.  Strategically, Murrawombie was developed to replace the now exhausted North East and Larsen underground mines.

Like Tritton, the Murrawombie deposit remains open at depth, presenting the opportunity for production to increase over time, and/or extending the life of the operation.

Ongoing grade control and geology mapping and modelling have provided a greater understanding of the Murrawombie orebody, which in turn has resulted in changes to mining methods to deliver improved and sustainable performance.   For example, sub-level caving has been abandoned in favour of more straightforward mining by sub level open stope design, allowing the extraction to be selective and enabling Aeris to target higher grade portions of the deposit.

Future changes in geology will be more modest and are not expected to require significant changes in mine design.  Find out more

 

Murrawombie Underground Mine Section View

 

Murrawombie Open Pit Mine Project

The expansion of the old Murrawombie Open Pit, which entails a small push back of the eastern wall to increase the pit depth, will allow Aeris to mine an estimated additional 1.6 million tonnes of ore.

The pit expansion project has secured Local and State Government approvals and from a regulatory perspective can proceed at any time. In the Life of Mine plan, the project is scheduled as the last mining activity on the Murrawombie deposit, with subsequent waste mined from the pit to be used for site rehabilitation and closure works. Use of the pit waste as capping for the adjacent heap leach pads substantially reduces the closure cost for the Murrawombie mine site.

The expanded pit will mine through the upper levels of the underground mine to recover stope pillars and remnants of the 101 and 103 lodes. These activities will destroy underground mine ventilation and backfill infrastructure, so mining of these areas is scheduled for after completion of the underground mining, or with minimal overlap in time.   Find out more

 

Murrawombie Open Pit Mine Extension

Mining Project - Budgerygar Deposit Conceptual Underground Mine 

The Budgerygar deposit is hosted within the Tritton stratigraphic package and is located some 600 metres to the north east of the Tritton deposit.  It has an Inferred Mineral Resource estimate of 2.3 million tonnes at 1.5% copper. There is low grade gossanous mineralisation outcrops at surface and portions of the deposit were mined intermittently during the early 1900s. The mineralisation is very similar to the Tritton deposit and is characterised by a large pyrite-dominant sulphide envelope, striking north-south and dipping moderately east. Copper mineralisation within the broader pyrite envelope is dominated by chalcopyrite. The copper rich zone is known over a strike length of 300 metres and has been traced 800 metres down dip, remaining open at depth.

Development of an exploration and access decline drive to the Budgerygar deposit has commenced. The access drive is being mined from the Tritton decline at 270 metres below the surface to provide a diamond drilling position, and eventually access for production. The exploration drive will allow for rapid diamond drilling to improve the resource estimate to at least Indicated Mineral Resource status.  Find out more

 

Long section of the Tritton Budgerygar Corridor

Mining Proejct - Budgery Deposit Conceptual Open Pit 

The Budgery deposit is approximately 20 kilometres south of the Tritton ore processing plant, close to the Hermidale township. It is located within the same geological setting as the Tritton and Murrawombie deposits and again, displays similar characteristics.

Significant exploration drilling has been conducted to support a concept study for an open-pit project, however additional Resource drilling, metallurgy studies, environmental studies and native title negotiations are required before a pre-feasibility study can be completed.

The proposed open-pit would mine a combination of oxide and sulphide ore types with the treatment method for the near-surface oxide portion of the ore body requiring additional technical work.  One option for the treatment of the oxide ore is by heap-leaching, a process with which Tritton Copper Operations is very familiar.  A second option is treatment through the Tritton ore processing plant with a sulphidisation pre-treatment. Both of these possibilities will be considered.

The Budgery mineralised system is significant and known to continue at depth. There has been limited drilling completed at depth, and this presents an opportunity to increase the Mineral Resource down-dip from the current reported Mineral Resource, which extends some 250 metres vertically. Options for selective underground mining of possible deposit extensions will be tested as drilling information becomes available. Find out more

Mining Project - Avoca Tank Underground Mine Project

Avoca Tank is a small, high-grade deposit located 5 kilometres to the north of Murrawombie. An application for a Mining Lease has been submitted. The current planned life of Avoca Tank is four years including construction, however there is a realistic expectation that exploration drilling could increase the size and life of the deposit.

Avoca Tank has multiple lenses of mixed chalcopyrite and pyrite mineralisation and it is likely that the complex structural character has contributed to its high grades. The deposit is unusual for the region due to its vertical dip, and it has an uncharacteristically high gold content at 0.8g/t.

As a small scale, high-grade mine Avoca Tank is planned to be mined as a supplementary ore source to top up production from the larger Tritton and Murrawombie mines. While a pre-feasibility study has already been completed, additional studies to optimise the mine access design, and to minimise environmental impact and closure costs will be reviewed in FY2020.

The pre-feasibility plan assumes a box cut and portal for a decline excavated from the surface located directly above the deposit. Mine infrastructure and waste dumps would be established next to the box cut, which requires the clearing of land and civil works. The alternative concept is to drive an access decline underground from the old North-East mine, using the existing portal in the Hartman pit. This underground access route would eliminate the surface disturbance, hence reducing the costs associated with environmental impact and infrastructure development. Find out more

Avoca Tank Development Application Environmental Impact Statement Documents 

Avoca Tank Environmental Impact Statement

Avoca Tank Environmental Impact Statement - Conditions of Consent

Avoca Tank Project Development Application Approval - Appendix  1

Avoca Tank Project EIS - Appendix 2 Director General Requirements

Avoca Tank Projects EIS - Appendix 3 Coverage of Director General Requirements

Avoca Tank Project EIS - Appendix 4 Statement of Committment

Avoca Tank Project EIS - Appendix 5 Aboriginal Cultural Heritage Assessment Part 1

Avoca Tank Project EIS - Appendix 5 Aboriginal Cultural Heritage Assessment Part 2

Avoca Tank Project EIS - Appendix 6 Ecology Assessment

Avoca Tank Project EIS - Appendix 7 Groundwater Impact Assessment

Avoca Tank Project EIS - Appendix 8 Noise and Blasting Assessment

Avoca Tank Project EIS - Appendix 9 Historic Heritage Assessment

Avoca Tank Project - Response to Submissions & Appendices June 2016

Avoca Tank Project Complaints Register

 

Avoca Tank and North-East Mine Infrastructure

 

Processing 

Ore from Tritton and Murrawombie  is transported to Aeris’ 1.8 million tonne per annum processing plant, located near the Tritton mine. Here the ore is processed through conventional crushing and flotation methods, producing a clean copper concentrate. 

Concentrate is transported by rail to the port of Newcastle, and is then shipped to smelters, predominantly in the Asia Pacific region.